Software Upgrade Categories Detail

Process Detail
Software Images
  1. Setup pointers to the software image locations. for the BS TRx OS, Application , SCRT, and Security Certificates as necessary for your hardware type. On a new system Initially there are no Image Files defined.

Image

  1. Click 'Add' to add additional pointers to the image code   

 

SS Configurations only

Software Version Expected in the Image file
Software Image File Suite
  1. Setup the Software Image File Suite this brings together the images to be downloaded). It will be referenced by individual nodes (BS TRx or SS) or by the Upgrade Categories to perform a system-wide upgrade.

 

 

  1. Click Add to add a new software image file suite. Add name, select  'Product Category Image' Click on software type in list and the click 'Edit'. Select file configuration and apply.

Note: In a new profile there is no software file configuration specified. It is necessary to select the number of the software type, then select ”EDIT”. A pulldown menu will be available under Software File Configuration allowing for one of the images defined in the previous step to be chosen.

Repeat 2 above for the other images to be grouped into the image file suite. The screen capture below shows a completed image file suite.

Upgrade Categories

Note: the download will only be to the BS TRx or SS hardware type which it is set to.

  1. Configure Software Management Product for global actions to be performed for the BS TRx shelf. There are entries for the SS, and different types of BS TRx.

Software Products

 

   Option 1: System Wide Upgrade

  1. Select the category and click edit. Once selected the product will have the following options under ”Request”

SS's also have the option to:

Software Products Edit

  1. To perform a system-wide upgrade this should be set to ”Download Software”, otherwise for individual BS TRx/SS upgrade leave as ”Idle”

  2. Schedule: If in 'allow edit' mode a request is made other than idle then a schedule box appears. If the box is checked new controls appear to selects the date and time for download to start and to finish, and the period in hours, minutes and days for download. If the schedule box is unchecked the request will be acted upon immediately.

  3. Click OK to initiate the download.

  1. To check progress of the download reopen the edit products window and observe the Statistics display

  1. After this process has completed the process needs to be repeated to Activate/Assign to Primary the software download .

   Option 2: Individual  Station Upgrade

  1. Open the Software Management Upgrade Categories. Select the category that is relevant and set to or leave as ”Idle”

Software Products Edit

  1. Go to the Configuration management screen. Select BS TRx or Subscriber Station and select the hardware to be upgraded form the list. More than one may be selected from the list using the Cntrl and Shift keys.  Click 'Edit' select the 'Software' tab. One can follow the global configuration setup in the previous step or override with a specific action and profile as shown below :

  1. Window with heading of ”Current Software Status” will be populated after changes have been made.

  1. Schedule: If in 'allow edit' mode a request is made other than idle then a schedule box appears. If the box is checked new controls appear to selects the date and time for download to start and to finish, and the period in hours, minutes and days for download. If the schedule box is unchecked the request will be acted upon immediately.

  2. To check progress of the install refresh the screen by clicking reload. (The stages observed are TFTP/FTP,installing, Bytes DL and Installed.) After the Application shows a status of Installed, the software can be activated.

Use 'Configure Software' tab and set the request to Activate (or Assign to Primary for SS if required). Click 'Apply'

  1. After swapping the Standby and Primary banks the Status changes to ”Rebooting”.  Note SS only: If Assign to Primary has been used for an SS the SS does not reboot and status becomes 'Idle'.

  2. After rebooting the hardware will run the new code. Note SS only: If Assign to Primary has been used for an SS the SS does not reboot until the Subscriber resets the SS or the SS is reset from the SS Management: Actions screen.

It is possible to have mixture of option 1 and option 2, to allow network-wide upgrade with some equipment specific upgrade (where overridden individually on Manage/Software tab on individual BS TRx or SS).