Operational voltage range: -40.5V to -57.0V.
Abnormal operation (without damage): 0 to -40.5V and -57.5 to -60V
(SCRT will operate down to -39volts with reduced brown out margin)
Procedure for terminating the DC supply for the SCRT at the SDR-Micro -48v DC source when using connectorised DC cable part numbers PWR-XX-INST-1 (where xx is cable length metres)
1. Run cable from the SCRT to the SDR-Micro The picture below shows the SDR end.
SDR END
2. Connect the cable at the SCRT
3. Connect the cable at the SDR-Micro
4. Do not apply power to the SCRT until the commissioning stage.
Run cable from the SCRT to the DC source breakers. (The SCRT end is the connectorised end)
SCRT
END
Connect the cable at the SCRT
Connect to the 48V DC Source distribution panel as follows
Polarity |
Colour |
Pin |
-48v |
Blue |
2 |
Return |
Black |
1 |